Ameren Illinois
Home Capacity RFP Energy RFP RECs RFP

Capacity RFP
Two types of capacity will be procured through the 2012 Capacity RFP for Ameren Illinois Company:
  • Planning Year 2012-13: Planning Resource Credits
MonthPRC Quantity
June 2012 1,910
July 2012 1,980
August 2012 1,830
September 2012 1,480
October 2012 1,120
November 2012 970
December 2012 1,030
January 2013 1,180
February 2013 1,090
March 2013 850
April 2013 860
May 2013 1,170

  • Planning Years 2013-14 and 2014-15: Zonal Resource Credits
YearZRC Quantity
2013-141,660
2014-151,110
Schedule
 
3/7/12
RFP and Draft Contract Issued
 
3/21/12
Contract Comments Due
 
3/21/12
Pre-Qualification Application and Bid Participation Fee Due
 
3/23/12
Pre-Qual Status Notifications
 
4/2/12
Final Contract Posted
 
4/3/12
Bidder Practice Session
 
4/3/12
Bidder Registration Deadline
 
4/5/12
Capacity Bids Due
 
4/6/12
Preliminary Bidder Notifications
 
4/11/12
Final Bidder Notifications
 
4/13/12
Contract(s) Executed

Documents
Request for Proposals (Posted 3/7/12)
RFP Attachment A - 2012-13 Confirmation Agreement
Comments should be redlined in Microsoft Word and submitted by email to aiurfp@levitan.com
Comment Deadline: 3/21/12, 12:00 noon CPT
No changes were made from the Draft 2012-13 Confirmation Agreement
RFP Attachment B - 2013-15 Confirmation Agreement
Comments should be redlined in Microsoft Word and submitted by email to aiurfp@levitan.com
Comment Deadline: 3/21/12, 12:00 noon CPT
RFP Attachment C - Form of Pre-Bid Letter of Credit
Requested Modifications should be redlined in Microsoft Word and submitted by email to aiurfp@levitan.com
Modification Submission Deadline: 3/21/12, 12:00 noon CPT
Pre-Bid Letter of Credit Submission Deadline: 4/3/12, 12:00 noon CPT
Instructions: Submit by email to aiurfp@levitan.com
Submission Deadline: 3/21/12, 12:00 noon CPT
Bidder Registration Form (Posted 3/7/12)
Submission Deadline: 4/3/12, 12:00 noon CPT
Supplier Fee Agreements will be executed with winning bidders, no action is needed until after awards are announced
The Supplier Fees for the Capacity RFP have been set at $0.50/PRC (MW-month) and $6.00/ZRC (MW-year)
Bid Submission
Bid Form (Posted 3/8/12, Updated 3/27/12)
Submission Instructions (Posted 3/8/12, Updated 3/27/12)
Submit Bid Form (Link will open a new window)
The binding bid submission window is now closed

Q&A
Submit a Question
#C8:
Please clarify / provide an example of how the capacity supplier fee will be assessed.
The supplier fee will be charged for each PRC or ZRC awarded within each product. For example if Bidder A is awarded 100 PRCs in July 2012, 250 PRCs in August 2012, 140 PRCs in March 2013 and 200 ZRCs in 2013-14, the supplier fee would be calculated as follows:
July 2012: 100 PRCs * $0.50/PRC = $50.00
August 2012: 250 PRCs * $0.50/PRC = $125.00
March 2013: 140 PRCs * $0.50/PRC = $70.00
2013-14: 200 ZRCs * $6.00/ZRC = $1,200.00
Total Supplier Fee: $50.00 + $125.00 + $70.00 + $1,200 = $1,445 payable to IPA within 7 business days of ICC ruling
(Posted 3/29/12)
#C7:
If implementation of the new MISO capacity market construct is delayed, how will the ZRC Confirmation Agreement be affected?
If Ameren Illinois Company is required to provide PRCs rather than ZRCs for one or both of the years covered under the 2013-15 Confirmation Agreement, the parties will convert the Contract Quantity of ZRCs to an equal amount of monthly PRCs over the entire planning period. For example, if implementation is delayed one year, and PRCs are required for the 2013-14 planning year, the ZRCs contracted for 2013-14 will be converted to monthly PRCs for that period. See page 2 of the Confirmation Agreement for the specific contract language.
(Posted 3/29/12)
#C6:
Please explain how a Zonal Resource Criteria would contain Minimum Offer Price Rule bid criteria.
MISO's proposed Minimum Offer Price Rule provisions are included in section 65.7 of the July 20, 2011 FERC filing in Docket No. ER11-4081.
(Posted 3/29/12)
#C5:
Please specify which proposed MISO Local Resource Zone is associated with Ameren Illinois Company's load?
Information from MISO indicates that the Local Resource Zones are still being defined, and a proposed map has not been filed with FERC. Preliminary information available from MISO's Supply Adequacy Working Group indicates that the Ameren Illinois Company load may be associated with Local Resource Zone 4.
(Posted 3/29/12)
#C4:
Where should the pre-bid letter of credit be sent?
The original pre-bid letter of credit should be sent to:
Timothy Moloney
Managing Supervisor, Credit Risk Management
Ameren Services
1901 Chouteau Avenue, MC 960
St. Louis, MO 63103
(Posted 3/29/12)
#C3:
When will the amount of the Capacity Supplier Fee be announced?
The Capacity Supplier Fee will be announced prior to bidding, an exact date is not available at this time, it may or may not be released prior to the Pre-Qualification Application submission deadline.
(Posted 3/19/12)
#C2:
Is the $100,000 Pre-Bid Letter of Credit the same Letter of Credit used to secure obligations under the 2012-2013 Capacity Confirmation Agreement, or is another separate Letter of Credit required under the 2012-2013 Capacity Agreement?
Yes, the $100,000 Pre-Bid Letter of Credit is the Letter of Credit used to secure obligations under the 2012-13 Capacity Confirmation Agreement, as referenced in paragraph 13 of the Confirmation Agreement.
(Posted 3/15/12)
#C1:
As long as an emailed or faxed copy of the pre-bid letter of credit is submitted by 12:00 noon CPT on April 3, 2012, is it acceptable for the original letter of credit to arrive after the deadline?
Yes, only the emailed or faxed copy of the letter of credit is required to meet the registration deadline, the original letter of credit can be received the following day.
(Posted 3/15/12)